Montrose Recreation Reserve Carpark Renewal

  • Project typeCarpark Renewal
  • Project value$300,000
  • Project scheduleConsultation/Design
  • Contractor nameTo be confirmed
ExistingCarparkImage#1.png

 

Following the adoption of the Montrose Recreation Reserve Master Plan in May 2020, renewal of the car park including sealing, line marking and lighting, was identified as a short-term project (0 to 2 years).  Delivery of the project was subject to Council budget allocations and capital works programming, and funding was not allocated until the current financial year.

In addition, a recent scheduled audit of the adjacent playspace identified structural issues, particularly with the timber elements. To address these issues, Council is developing a draft concept design for the renewal of the playspace. Initial community engagement for playspace renewal was undertaken in November 2025, generating nearly 400 responses. While the majority of feedback related to the playspace, several submissions also highlighted the need for improvements to the car park, including sealing the surface and installing lighting.

Council had been exploring opportunities to coordinate delivery of the playspace renewal and car park renewal projects where feasible. However, the timing of available State Government grant opportunities and broader funding considerations have influenced the proposed delivery program. Subject to future funding and approvals, the playspace renewal is anticipated to proceed in the following phase, with completion currently targeted for mid-2028.

What we are doing

  • Sealing the current gravel car parks located on the north side of the reserve
  • Formalising car spaces by line-marking bays
  • Providing kerb and channel throughout the car parks to manage stormwater runoff as well as delineate the area
  • Provide new underground drainage to better manage the current overland flow of water
  • Construct new concrete footpaths to improve pedestrian access to/from the car parking areas
  • Construction of a raised pedestrian crossing to provide safer access across the service road
  • Construction of road humps and a raised platform (pedestrian crossing) to support safer vehicle speeds and improve awareness of pedestrian activity within the zone
  • New lighting around the car park zone

Next Steps

Following stakeholder consultation, we will complete engineering design and seek expressions of interest for construction.

Construction Timeline

Anticipated between April and June 2027